close
MENU
Hot Topic Hawke’s Bay
Hot Topic Hawke’s Bay
Politics
2 mins to read

Transmission Gully crosses $1b mark

The project is expected to open by Christmas.

Andrew Bevin Fri, 14 Feb 2020

The Transmission Gully project has ballooned to over $1 billion, with the New Zealand Transport Agency agreeing to pay the sub-contractor $190.6m.

The sub-contractor, CPB HEB JV was seeking $352 million in compensation over delays in starting the work, including the 2016 Kaikoura earthquake and

Want to read more? It's easy.

Choose your best value subscription option

Student

Exclusive offer for uni students studying at a New Zealand university (valued at $499).
Individual
Group membership
NBR Marketplace

Yearly Premium Online Subscription

NZ$499.00 / yearly

Monthly Premium Online Subscription

NZ$44.95 / monthly

Smartphone Only Subscription

NZ$24.95 / monthly

Premium Group Membership 10 Users

NZ$350+GST / monthly

$35 per user - Pay by monthly credit card debit

Premium Group Membership 20 Users

NZ$600+GST / monthly

$30 per user - Pay by monthly credit card debit

Premium Group Membership 50 Users

NZ$1250+GST / monthly

$25 per user - Pay by monthly credit card debit

Premium Group Membership 100 Users

NZ$1875+GST / monthly

$18.75 per user - Pay by monthly credit card debit

Yearly Premium Online Subscription + NBR Marketplace

NZ$499.00 / yearly

Already have an account? Login
Andrew Bevin Fri, 14 Feb 2020
Contact the Writer: andrew@nbr.co.nz
News tip? Question? Typo? Let us know: editor@nbr.co.nz
© All content copyright NBR. Do not reproduce in any form without permission, even if you have a paid subscription.
Transmission Gully crosses $1b mark
Politics,
82558
true